Saturday, July 25, 2009

Mark Your Calendar!

Parish Center Dedication
August 29, 2009
11am

The parish center is getting closer and closer to completion every day.
This morning a great number of parishioners helped sod the outside of the building. Pictures coming soon.

continue to pray for the parish community as we diligently prepare for the dedication of our parish center.

Wednesday, June 3, 2009

May 2009






Amazing how much building can happen in just a month! from the outside it looks as if the parish center at St. Albert the Great is nearly complete... we know there is still much left to do, but it is looking quite fabulous! Here are some pictures to document the last month or so in the life of the construction phase of our new building! More to come!



Thursday, April 30, 2009

April at Brickey Lane




Sand volleyball is nearing completion Grilling area near pavillion will have 3 built in grills

Wednesday, April 1, 2009






The Building Committee met on 3/23, the committee unanimously decided to remove the 4 classrooms along the rear of the nave. The committee felt that with the continued weekly growth in mass attendance, the parish would soon outgrow the worship space as detailed. Removing the classrooms would both improve the asthetic and functionality of the new building.




























Thursday, March 19, 2009

March 19, 2009


As thousands pile into the Convention Center to welcome our new Bishop, Richard Stika, the work on Brickey Lane continues!


This is an image of the first truss going up on Tuesday, March 17

Wednesday, March 11, 2009

Parish Center 3-11-09

Again, the face of Brickey Lane is changing!

This week the small steel beams are in place on the exterior of the building, the brick work is beginning, and the insulation board is being placed this week!


Below is a picture of the site as it looked yesterday afternoon!

March 10, 2009


Wow, it's amazing what a week of beautiful weather and willing hands will do for the Brickey Lane Property!


Many people have been hard at work on the walking trail, as it nears completion here's a shot of Larry Roovers working on the trail this week!



Thursday, March 5, 2009

putting up the steel




The crane is here to erect the steel
Later in the day, the steel is in place

Thursday, February 5, 2009

January 2009

January 2009 Update!
The footers and support columns have all be poured and the mason has started laying block.
The electric and plumbing have all be roughed in and the steel is scheduled to be put in place this week!
It's not much to look at from the surface, but it's been busy over here on Brickey Lane!
Check back soon, with the steel set and the block being laid, there will be a much more to look at in the very near future!

Tuesday, January 13, 2009

We are under Construction!


The rain has broken, for the moment. As I look out the front window of office on Brickey Lane I see men working, trucks moving, rumor has it that some footers will be poured this afternoon. It's a glorious day on Brickey Lane! Watch the blog closely for the next few months as we walk through every aspect of the building process. i'll show you some pictures and tell you a little bit about the progress of the building!

Tuesday, January 6, 2009

Rain Rain Go Away

We are so blest to have the much needed rain at Brickey Lane!!
It has, however, stalled the progress on our building project! The site is ready to go, the parking lot is leveled the equipment is on the lot, and the electricity is connected.
The office has been hard at work setting up billing accounts and filing tax exempt forms.
Now, we wait. We thank God for the gift of rain, and pray that sooner than later we have a few windows of sun in order to lay footers, then we will be on our way!

As always we ask your continued prayers for the St. Albert the Great Parish and the building project.