Thursday, June 26, 2008

June 23rd Meeting

Saint Albert the Great Parish
Building Committee
Monday, June 23, 2008


Opening Prayer: Kristen Lehman

Budget & Timeline: See Previous Post

Site Development on “fast track” (July/August) – we will have a rough grading package put together for next meeting, to apply for permit.

Design build/Design Contractor Team – Discussion concerning whether or not to have a contractor with us through the design process or bid out after the design is determined.

The Architects provided detailed brochures from 7 general contracting firms. Deacon Mike will assemble a sub-committee to review and make recommendations at the next meeting.

Environmentally friendly options: Decision to not seek LEED certification, but to continue to think “green” as we move through this process.

Continue to check the back of the bulletin for Campaign updates

Review of Building Plan – Seating capacity 380 with 24” seats.
Updated building plan, watch for updated drawing on the Blog.
Architects will work with a computerized 3D model to test daylight options.
At next meeting will review elevations, window placements stairs/ramps etc.

Please continue to pray for the success of the campaign as we work to bring the building process to completion.

Entrance sign – Interest in making the sign both permanent and have some changeability, will discuss more at next meeting.

Pavilion – will move forward when exterior drawings of building are more concrete.

Next Meeting: July 7, 2008

Closing Prayer: Larry Rossini