The Building Committee met on 3/23, the committee unanimously decided to remove the 4 classrooms along the rear of the nave. The committee felt that with the continued weekly growth in mass attendance, the parish would soon outgrow the worship space as detailed. Removing the classrooms would both improve the asthetic and functionality of the new building.
Thursday, March 19, 2009
March 19, 2009
Wednesday, March 11, 2009
Parish Center 3-11-09
Again, the face of Brickey Lane is changing!
This week the small steel beams are in place on the exterior of the building, the brick work is beginning, and the insulation board is being placed this week!
March 10, 2009
Thursday, March 5, 2009
Thursday, February 5, 2009
January 2009
The footers and support columns have all be poured and the mason has started laying block.
The electric and plumbing have all be roughed in and the steel is scheduled to be put in place this week!
It's not much to look at from the surface, but it's been busy over here on Brickey Lane!
Check back soon, with the steel set and the block being laid, there will be a much more to look at in the very near future!