Saturday, July 25, 2009

Mark Your Calendar!

Parish Center Dedication
August 29, 2009
11am

The parish center is getting closer and closer to completion every day.
This morning a great number of parishioners helped sod the outside of the building. Pictures coming soon.

continue to pray for the parish community as we diligently prepare for the dedication of our parish center.

Wednesday, June 3, 2009

May 2009






Amazing how much building can happen in just a month! from the outside it looks as if the parish center at St. Albert the Great is nearly complete... we know there is still much left to do, but it is looking quite fabulous! Here are some pictures to document the last month or so in the life of the construction phase of our new building! More to come!



Thursday, April 30, 2009

April at Brickey Lane




Sand volleyball is nearing completion Grilling area near pavillion will have 3 built in grills

Wednesday, April 1, 2009






The Building Committee met on 3/23, the committee unanimously decided to remove the 4 classrooms along the rear of the nave. The committee felt that with the continued weekly growth in mass attendance, the parish would soon outgrow the worship space as detailed. Removing the classrooms would both improve the asthetic and functionality of the new building.




























Thursday, March 19, 2009

March 19, 2009


As thousands pile into the Convention Center to welcome our new Bishop, Richard Stika, the work on Brickey Lane continues!


This is an image of the first truss going up on Tuesday, March 17

Wednesday, March 11, 2009

Parish Center 3-11-09

Again, the face of Brickey Lane is changing!

This week the small steel beams are in place on the exterior of the building, the brick work is beginning, and the insulation board is being placed this week!


Below is a picture of the site as it looked yesterday afternoon!

March 10, 2009


Wow, it's amazing what a week of beautiful weather and willing hands will do for the Brickey Lane Property!


Many people have been hard at work on the walking trail, as it nears completion here's a shot of Larry Roovers working on the trail this week!



Thursday, March 5, 2009

putting up the steel




The crane is here to erect the steel
Later in the day, the steel is in place

Thursday, February 5, 2009

January 2009

January 2009 Update!
The footers and support columns have all be poured and the mason has started laying block.
The electric and plumbing have all be roughed in and the steel is scheduled to be put in place this week!
It's not much to look at from the surface, but it's been busy over here on Brickey Lane!
Check back soon, with the steel set and the block being laid, there will be a much more to look at in the very near future!

Tuesday, January 13, 2009

We are under Construction!


The rain has broken, for the moment. As I look out the front window of office on Brickey Lane I see men working, trucks moving, rumor has it that some footers will be poured this afternoon. It's a glorious day on Brickey Lane! Watch the blog closely for the next few months as we walk through every aspect of the building process. i'll show you some pictures and tell you a little bit about the progress of the building!

Tuesday, January 6, 2009

Rain Rain Go Away

We are so blest to have the much needed rain at Brickey Lane!!
It has, however, stalled the progress on our building project! The site is ready to go, the parking lot is leveled the equipment is on the lot, and the electricity is connected.
The office has been hard at work setting up billing accounts and filing tax exempt forms.
Now, we wait. We thank God for the gift of rain, and pray that sooner than later we have a few windows of sun in order to lay footers, then we will be on our way!

As always we ask your continued prayers for the St. Albert the Great Parish and the building project.

Thursday, November 20, 2008

parish Groundbreaking!


Nothing speaks more strongly about the community here at St. Albert the Great Parish than to the tremendous support on Saturday November 15th for the groundbreaking of our Parish Center. We estimate that over 300 people joined us on a cold, rainy, windy Saturday to break bread (or Ribs) then Break ground. It was truly blessing to be part of such a wonderful day!


Check out the Youtube slideshow (thanks to our very own Deacon Patrick Murphy-Racey)




Check out the news sentinal article at:



Below is the picture featured in the News Sentinel Article





The pavillion under construction!









Pavillion is done!




there is so much to report in the building process at St. Albert the Great! Thanks to everyone who put sweat equity into the picnic pavillion! See below for more pictures!

Thursday, October 16, 2008

Groundbreaking

Mark your Calendar!!
The Parish Ground breaking will be held on November 15 time TBA
We invite everyone (children too) to bring a shovel or a spoon or other tool to help break ground.
We will begin the festivities with a nice meal, followed by the ground breaking ceremony.
check back for more information.

September 2008

Greetings!
as we progress quickly with the building of the Parish Center, it is easy to see that a lot is happening. The ground has been leveled and is awaiting patiently the ground breaking on November 15. There are trucks on Brickey Lane almost daily digging footers for the new picnic pavillion, laying ground for a parking lot expansion, and putting in a new sewer line.

The Diocese has approved out proposal! Evans Construction will begin the bidding process next week. We will review the bids and make a final recommendation to Parish Council at their November meeting.

In addition the stained glass window designer (Bill May) and baptismal font designer (Scott DeWard) have presented samples for review. Check back soon for pictures!

Thank you to the interiors Committee as well as the plans review committee. their hard work and dedication will both expediate and simplify the building process.

Check back frequently as the building starts to come out the ground...
We will post pictures and updates weekly as we walk through the property!

Tuesday, August 26, 2008

Meeting August 18

Opening Prayer: John Kerwin

Architect Presentation: A few minor changes were made to the floor plan, including door placement in classrooms, doors into sanctuary, and organization of storage area behind the altar.

Entrance Sign: An initial design was presented. Thoughts are to have 2 signs. 1 close to Brickey Lane with the name of the parish and one down the driveway with coming events, Mass times, and other information.

Covered Walkway: A brief discussion was held concerning a covered walkway. Discussion centered on the need for the walkwayto be built on the back of the building and to connect to the handicapped parking.

Classroom space: Discussion revolved around the need to consider future use of the parish hall and ease of wall removal to provide more space. No decision was made concerning the classrooms in the back of the parish hall.

Site Work Update:
Progress Report: Stripping of the top soil almost complete; major cut and fill operations to begin shortly.
Decision was made to fast track the design of Phase II grading (parking, retention and driveway widening)

Contractor Update:
Evans will continue to modify cost estimates as more information is gathered about building materials and finishes
Steve will give Fr. Chris an updated cost estimate for the diocesan proposal and have an official proposal complete for the next meeting

Pavilion Update:
Drawings were presented and approved. Architect and engineer will continue to tighten up the design and send them to the county for initial review.
Committee decided to not push the pavilion toward completion for the picnic but to build it as it makes sense.

Construction Plans Committee:
Will most likely review plans in small groups over the next week.
"Green" items to continue to discuss:
Rain water retention
Energy Efficient lighting
Solar Hot Water for Bathrooms and sacristy
Recycling

Interior Finishes committee
Baptismal font
Stained glass
Dedication plaque

Next meeting date: Monday September 15 6:30pm

Closing Prayer: Dan Alexander

Thursday, July 24, 2008

Meeting July 21

St. Albert the Great ParishBuilding CommitteeMonday, July 21, 20086:30 pm

Meeting was held by candlelight thanks to the storm.
1) Opening Prayer: Deacon Mike
2) Introduction of Evans Construction as our Design/Build Contractors. They shared with the committee about their experience and dedication to this project.
3) Issues from last meeting
a. Site work on Fast Track – it was decided to do the site work in 2 phasesb. Phase 1: Grading for Parish Center Building Site & Picnic Pavilion – All appropriate permits have been applied for; we hope to be “moving ground” by August 1.c. Phase 2: Grading for parking lot & water retention basin soon thereafter4) The committee reviewed the latest drawings of the building interior and exterior.Johnson Architecture presented a new conceptual drawing for the parish center.
They tamed the lines of the exterior of the space, and opened up the interior ceiling.
The committee engaged in a lengthy discussion of the pros and cons of each as well as exterior materials, brick, vinyl, stucco, stone. No decisions were made.
Architects to continue to explore the 2 designs and use similar color scheme to the existing house. They will have a new presentation at the next meeting.
5) Jim Hinton & Bill Morgan will be working on the pavilion plans
Jim will have plans at next meeting.
It was agreed that the concrete pad and the frame for the building will be set by the grading contractor.
6) The architects are still working on an entrance sign.

7) Evans Construction will present us with preliminary estimated cost for our building designs at the next meeting - this will allow us to determine if we are in the ballpark with the designs currently under consideration.

8) 2 subcommittees are to be formed soon:
a) Textures, colors – interior
b) Plans review (construction documents etc)
9) Next Meeting: August 4th 6:30 pm10) Closing Prayer: Father Chris

Wednesday, July 9, 2008

Architect Drawings










Front View












interior view










View from drive









View from Brickey Lane









Interior view

Tuesday, July 8, 2008

Building meeting Monday, July 7, 2008

St. Albert the Great Parish
Building Committee
Monday, July 7, 2008
6:30 pm

No MPC review needed
No traffic study needed at this time

1) Opening Prayer: Bill Morgan
2) Issues from last meeting
a. Site work on Fast Track – it was decided to do the site work in 2 phases
b. Phase 1: Grading for Parish Center Building Site & Picnic Pavilion – with all appropriate permits in place, we hope to be “moving ground” by August 1.
c. Phase 2: Grading for parking lot & water retention basin soon thereafter
3) Traditional Design/Bid/Build vs. Design/Build
a. Consensus to go with a design/build approach; this means we will be adding a Contractor to the Design Team ASAP.
b. The sub-committee consisting of Fr. Chris, Deacon Mike, David Nevin & Jim Hinton narrowed the contractor field to 3 names. Evan, Merit & Messer construction. Each of these contractors will be interviewed next week and the results will be presented to the building committee at the next meeting.
4) The committee reviewed the latest drawings of the building interior and exterior.
Many suggestions were made concerning windows, exit doors, window height, choir location etc.
The architects will redesign and present revised drawings at the next meeting. Check back soon for that design.
5) Jim Hinton & Bill Morgan will be working on the pavilion plans
6) The architects have begun work on designing an entrance sign, they will have more detailed information next meeting.
7) Next Meeting: July 21st 6:30 pm
8) Closing Prayer: Kathy Walker